Bengaluru's power cuts are back on the calendar, and BESCOM is calling them preventive
More than 100 localities appeared on the January 21 shutdown list for a single substation job. The outage is eight hours. The calendar around it is the story.
By Priya Shankar · Bengaluru Correspondent, Bengaluru & Karnataka

The short version
- BESCOM scheduled an eight-hour shutdown on January 21, 2026 for maintenance and emergency works at the 66/11 kV Banaswadi substation.
- More than 100 localities across east, north, central and south-east Bengaluru were on the list, with supply expected to be cut from 10am and restored by evening.
- Earlier in January, BESCOM ran overlapping feeder maintenance schedules in Tumkur, Davangere and Kolar, and separately replaced conductors on the 66 kV Sarjapura-Attibele line.
Bengaluru began January with the power cuts it has learned to schedule around. The pattern is now so familiar that it is worth describing precisely rather than as a complaint: a substation, a daytime window, a list of localities that appears in advance, and a helpline number. The January 21 shutdown was declared for the 66/11 kV Banaswadi substation, where BESCOM said maintenance and emergency works were required, with supply to be cut from around 10am and restored by evening depending on how quickly the work finished.
- Window: 10am to 6pm on January 21, 2026, an eight-hour daytime shutdown.
- More than 100 localities affected, concentrated in east, north, central and south-east Bengaluru.
- Named areas include HRBR Layout, Kammanahalli Main Road, CMR Road, Hennuru, OMBR Layout, Kasturi Nagar, Ramamurthy Nagar Main Road, B Channasandra and Rajkumar Park.
- BESCOM's advice: charge essential devices, plan work-from-home schedules, use power backup where available, and exercise caution when restoring supply.
Why before summer
The reason a single substation dominates the January list is that the work is deferred until it can be done in daylight. The Hindu reported that outages on the city's outskirts on January 17 and 18 were scheduled for replacement of the existing 66 kV Sarjapura-Attibele single-circuit coyote line with high temperature low sag conductors, and for stringing a second circuit on the same route, alongside work at the Attibele, Samanduru, Anekal and Chandapura substations. Industrial loads were being moved to night hours so that daytime work could proceed.
The density of the January calendar is the part that residents notice. BESCOM notices published on January 6 covered feeder maintenance in Tumkur on January 4, 6, 8, 10, 12, 14 and 16, emergency repairs in Davangere, and link line work in Katsandra between January 5 and 8. A further alert covered intermittent outages across Tumkur through January 27 and a third-quarter maintenance shutdown at the 220 kV receiving centre in Kolar on January 25. None of it is unscheduled, and all of it adds up.
Sources — 6 references
These are the published sources this article was established against. NOT SCRIPTED wrote the text above; the sources below are credited to their own publishers.
- News18 (opens in a new tab)
- Goodreturns (opens in a new tab)
- Oneindia (opens in a new tab)
- The Hindu (opens in a new tab)
- Goodreturns (opens in a new tab)
- Goodreturns (opens in a new tab)
Affected-area lists differ slightly between outlets that truncate; only localities named in more than one notice are listed in the article.
About the byline
Priya Shankar
The city's infrastructure, water and traffic problems, and the politics of fixing them.
Read about the NOT SCRIPTED newsroom and how our bylines work.
Related coverage

Bengaluru's Green Line runs in a short loop for 45 minutes after a power breakdown

TCS opens an NVIDIA-backed industrial AI lab on its Bengaluru campus

BJP asks the Governor to probe the Bengaluru solid-waste tender awarded for 30 years